We are delighted to announce that construction is well underway at Century Square. Take a look at the build programme in more detail below.

Progress and Programme
Programme week 4

  • Site Set up and compound is as per the CPP and heras fencing is in place.
  • De- gassing of ac units on floors 2 and 3 is completed and we are awaiting certification for this.
  • Strip out is completed on floors 2,3 and skip locations have changed along with the site management plan.
  • Ground floor and 4th floor strip out under way.
  • First fix electrical has started on site on the 3rd floor and the mains have been pulled in to the 3rd and 2nd floors
  • First Fix stud works, and boarding have been completed on the 3rd floor and the second floor
    80% completed, all materials on site for further floors
  • Hoarding of the site and traffic management is now completed
  • We have also had various telecoms company’s come to site and carry work on the masts.
    this is an ongoing situation.



century square

Activities to be started & ongoing in the next 4 weeks:

  • Strip out will continue the ground,4th and 5th
  • First Fix electrical to 3rd and 2nd floor
  • First fix stud work to 2nd and 4th floor will be completed
  • First fix ventilation to the 3rd floor.
  • Sprinkler install to 3rd floor.
  • First fix plumbing to 3rd and 2nd floor
  • Mf Ceiling install and 2nd side boarding to 3rd floor
  • Plastering to 3rd floor
  • Mist coat to 3rd Floor
  • Tiling to 3rd floor
  • Window survey to 3rd floor – install end of August – subject to planning
  • Install of sub floor to 3rd floor
  • Install of good hoist 8th August